Local News
Correction regarding details of courthouse restoration
By Allen Rich
May 16, 2019
Print this page
Email this article

I want to issue a correction regarding details of courthouse restoration.

In a previous article, I stated that Turner Construction, the Construction Manager-Agent on this project, is not allowed to work on construction and cannot be a party to any of the construction subcontracts.

In this particular case, there is no such stipulation between Fannin County and Turner Construction.

Turner Construction has solicited from the county on April 9, 2019, approval for Turner Self-Perform Organization (SPO) to bid on Turnkey Concrete, Site Logistics and Specialties.

The article also stated that work on Fannin County Courthouse would begin April 1, 2019, with a substantial completion date of October 3, 2020.

The latest schedule calls for a start date for phase 1 to begin May 20, 2019, with a substantial completion date of February 9, 2021.

 -- Allen Rich