Proposed improvements include:
· Constructing two 12-foot wide inside travel lanes and one 14-foot outside shared-use path with raised median and curb and gutter in each direction on FM 1515
· Constructing sidewalks in each direction on FM 1515
· Replacing the existing bridges over Dry Fork Hick Creek, the Kansas City Southern Railroad and I-35W
· Constructing left-turn lanes and a roundabout at FM 1515 and Masch Branch Street
This is the first opportunity for public input on the estimated $40 million project.